Capital Investment Projects

The Town of Chesapeake and the City of Chesapeake Sanitary Board are investing in the community’s infrastructure – removing blight, lowering energy costs and rebuilding the sewer system – using state and federal grants and low-interest financing to keep the cost to residents as low as possible.

Overview

ProjectStatusInvestmentFundingResult
WV DLAP – Dilapidated StructuresCompleted & closed (Aug. 2026)$260,000WV DEP grant, fully reimbursed21 structures addressed: 19 demolished, 2 abated and to be demolished by owners
Energy EfficiencyCompleted & closed$34,830U.S. DOE grant through WV Office of EnergyAll windows in Town Hall replaced with energy-efficient windows
Sewer RehabilitationPhase 1 in pre-construction; Phase 2 plannedPhase 1 $4,483,403; Phase 2 est. $4,043,500IJDC grant, CWSRF principal forgiveness and low-interest loan, Town ARPA funds5 lift stations and about 16,400 feet of sewer and force main to be replaced or upgraded

Select a project below to expand its details.

WV DLAP – Dilapidated Structures Removal
Completed & closed$260,000

Status: Completed and closed. The Town received a $260,000 grant from the West Virginia Department of Environmental Protection (WV DEP) Dilapidated Properties Program (DLAP) to demolish unsafe, abandoned structures.

21
dilapidated structures addressed
19
demolished under Town contract
2
abated by the Town, to be demolished by their owners
$260,000
grant – fully spent and reimbursed
What was done
  • Legal tools. The Town adopted the State Building Code rule and the 2018 International Property Maintenance Code (March 2024) and an ordinance for vacating, closing or demolishing unsafe structures (June 2024).
  • Application. In September 2024 the Town applied to DLAP, documenting 67 dilapidated structures and an estimated $856,000 of need.
  • Award. WV DEP awarded the Town $260,000 in November 2024.
  • Historic review. Structures were submitted to the State Historic Preservation Office for review and approval before demolition.
  • Round one. Four dilapidated houses were demolished in September 2025, debris removed and sewer lines capped.
  • Homeowner assistance. In April 2025 Council adopted a demolition assistance policy – a sliding-scale grant covering 80–100% of costs for verified low-income homeowners.
  • Round two. Bid competitively in spring 2026: four contractors attended the pre-bid conference, bids were opened in public on May 7, 2026, and Council awarded the contracts by resolution.
  • Public health. All 19 Town-contract structures had been occupied by squatters, many without water service for ten years or more. Asbestos was removed wherever present, and every sewer line was dug up and capped at the main.
  • Reinvestment. In July 2026 Council voted 5–0 to reinvest $34,000 of grant reimbursements to keep the program going.
  • Closeout. The final report was filed August 26, 2026, with every dollar spent. WV DEP confirmed the $260,000 award was fully reimbursed and the grant closed. Successful completion preserves the Town’s eligibility for future DLAP awards.
Demolition Grant Funds for Property Owners

Own a dilapidated house or structure in the Town of Chesapeake but can’t afford to tear it down? The Town’s Demolition Assistance Policy, adopted by Council in April 2025, offers a sliding-scale grant covering 80% to 100% of demolition costs for verified low-income homeowners.

  • Who qualifies: owners of dilapidated structures in the Town whose household income is verified as low-income.
  • How much: the grant covers 80% to 100% of the cost of demolition, based on a sliding scale.
  • Funding: demolition is funded through WV DEP Dilapidated Properties Program grants and Town funds, including grant reimbursements Council reinvested to keep the program going.

To ask about assistance: contact Town Hall at 304-949-1496 or townhall@chesapeakewv.gov, 12404 MacCorkle Ave., Chesapeake, WV 25315.

Looking ahead

More than 60 dilapidated properties are inventoried; the 21 addressed under this grant are the start. Code enforcement has also led owners to demolish about five more structures at their own expense. The Town holds a one-year open-end demolition contract, renewable for up to four more years, will continue with Town funds, and will apply for future grant rounds. Liens are being recorded to recover the Town’s costs.

Report a dilapidated or abandoned structure: use 311 Chesapeake – Report a Concern and choose “Abandoned Building/Home” or “Vacant Property/Home.” Owners of vacant property can use Vacant Property Registration.

Energy Efficiency – Town Hall Windows
Completed & closed$34,830

Status: Completed and closed. The Town received an Energy Efficiency and Conservation Block Grant (EECBG) from the West Virginia Office of Energy, funded by the U.S. Department of Energy, for its project “Chesapeake Green Forward: Advancing Energy Efficiency and Sustainable Infrastructure for Community Resilience.”

About the Grant
$34,830
total grant award
$34,795
window replacement contract
12404
MacCorkle Ave. – Town Hall
  • About the program. The Energy Efficiency and Conservation Block Grant program was funded by the Bipartisan Infrastructure Law to help local governments reduce energy use and improve energy efficiency. The U.S. Department of Energy allocated $1,809,210 to West Virginia, and the West Virginia Office of Energy awarded competitive subgrants to smaller local governments.
  • Application and award. The Town applied in October 2024. The Grant Award Notice and Memorandum of Understanding with the West Virginia Office of Energy were signed March 14, 2025, for $34,830 and a project period of March 14, 2025 through October 30, 2026.
  • Purpose. To modernize Town facilities for better energy performance, lower operating costs and improved comfort, including the retrofit and replacement of outdated windows and doors.
  • Why it was needed. Town Hall is housed in a former school building of about 9,600 square feet, and its windows and doors were not energy efficient.
Project Work and Closeout
  • Progress reporting. The Town filed quarterly reports with the WV Office of Energy. As reported in October 2025, planning was complete, and because the vendor required 50% payment up front, installation was scheduled later in the year to manage cash flow until reimbursement.
  • The work. All windows in Town Hall, 12404 MacCorkle Ave., were replaced with energy-efficient windows by Window World.
  • Funding the deposit. The required 50% deposit ($17,397.50) was advanced from Coal Severance ($4,000), opioid settlement funds ($5,000) and the General Fund ($8,397.50). Those funds are being restored from the grant reimbursement.
  • Closeout. The windows are installed, final payment was made, the grant reimbursement was received and the final report was submitted.
Sewer Rehabilitation – Wastewater System Improvements
Phase 1 pre-construction · Phase 2 planned$8.5 million (2 phases)

Status: Phase 1 in design and pre-construction; Phase 2 planned. The City of Chesapeake Sanitary Board is carrying out a two-phase project to rebuild key parts of the sewer system. The engineer is Burgess & Niple. The project is required to meet the terms of the Sanitary Board’s 2018 settlement agreement with the WV Department of Environmental Protection.

$4.48 million
Phase 1 – funded
$4.04 million
Phase 2 – estimated
5
lift stations replaced or upgraded
~16,400 ft
of sewer and force main replaced
Why it is needed
  • Sewer overflows. The goal of the project is to eliminate sanitary sewer overflows. To do that, all five lift stations need more capacity and the gravity sewers need less inflow and infiltration (I&I).
  • Stormwater and groundwater in the sewer. Runoff and groundwater leak into aging lines, sending clean water to the treatment plant, raising treatment costs and overloading the lift stations.
  • Survey findings. The Sewer System Evaluation Survey identified the lift stations and key sewer lines to fix first, along with improper service connections.
  • Doing nothing is not an option. The engineer’s report found that without the project the aging system will worsen, keep harming the community, and leave the Sanitary Board out of compliance with its settlement agreement.
The Two Phases
Map of the Town of Chesapeake wastewater system improvements showing existing sewer (red), force main (blue), Phase 1 project (yellow) and Phase 2 project (orange)
Town of Chesapeake Wastewater System Improvements – project map presented at the May 26, 2026 public meeting (Burgess & Niple). Yellow: Phase 1 project. Orange: Phase 2 project. Red: existing sewer. Blue: force main. Click the map to enlarge.
Phase 1 (yellow on map)Phase 2 (orange on map)
Lift stationsTwo lift stations replaced with new, higher-capacity stations in new locationsThree lift stations upgraded
Force mainAbout 3,900 feet of new PVC force main, including a new line to the Marmet treatment plantAbout 2,400 feet of PVC force main replaced
Gravity sewerAbout 3,900 feet of new PVC sewer, 30 manholes replaced and 65 service connectionsAbout 6,300 feet of new PVC sewer, 35 manholes replaced and 70 service connections
StreetsIncluding Venable Avenue, Kanawha Avenue, 115th Street and Nancy AvenueSee map
Construction (with contingency)$3,406,500$3,177,000
Total project cost$4,483,403 (approved funding)$4,043,500 (estimate)
FundingApproved by IJDC – see belowProposed: $500,000 IJDC grant, $1,500,000 CWSRF principal forgiveness and a $2,043,500 CWSRF loan; the grant may rise to $1,000,000 and the loan rate fall if sewer rates reach 2% of median household income
  • Phase 2 next steps. Phase 2 will require a sewer system consolidation assessment before it moves forward. The 7% Step 2 rate increase follows completion of the project (TBD 2+ years).
  • How the estimate developed. The July 2025 conceptual estimate put Phase 1 at $4,264,100 and Phase 2 at $3,582,000. The September 2025 update put Phase 1 at $4,297,700 and Phase 2 at $4,043,500, mainly because Phase 2 gravity sewer replacement grew from about 4,400 to about 6,500 feet. The approved Phase 1 budget of $4,483,403 is the September Phase 1 estimate plus repayment of the $185,703 in planning-phase funding.
  • Why PVC. The engineer compared PVC and ductile iron pipe. PVC was selected because it costs less over its life, is faster and safer to install, and resists corrosion from sewer gases better.
  • Operating costs. Operating costs stay about the same except for added electricity for the larger lift stations – about $3,304 a year after Phase 1 and $2,371 a year after Phase 2.
  • Playground reopening. A Town playground closed after a sewage overflow at the neighboring lift station. Phase 1 relocates that lift station downstream so the playground can reopen after construction and cleanup.
  • Environment. Work will be in previously disturbed ground, mostly existing roads. The contractor must follow the construction stormwater permit, including silt fences, seeding and regular cleanup, and work normal hours to limit noise.

Sources: Burgess & Niple Preliminary Engineering Report (draft, October 2025); Conceptual Cost Estimates – 2-Phased Approach (July 2025 and September 2025).

Planning Phase – Sewer System Evaluation Survey (2022–2025)

In July 2022, the West Virginia Water Development Authority, at the direction of IJDC, entered into a Pre-Application Funding Assistance (PFA) agreement with the City of Chesapeake Sanitary Board to pay for the Sewer System Evaluation Survey (SSES), the preliminary engineering report and the funding application for this project.

  • Budget: $442,500 – up to $192,500 of IJDC funding assistance and a $250,000 local contribution.
  • Actual spending: $185,702.75 from IJDC and $224,702.74 from the Town’s ARPA funds.
  • Repayment: under the agreement, PFA funding becomes a grant only if the project is not approved. Because the approved project includes a loan, the $185,703 of IJDC funding is repaid from the CWSRF loan at closing.
  • Result: the SSES identified the needed repairs, and the Sanitary Board’s preliminary application was approved by IJDC on January 7, 2026.
Phase I Funding – Sewer Line Upgrade/Replacement

On January 7, 2026, the West Virginia Infrastructure and Jobs Development Council (IJDC) approved the Sanitary Board’s preliminary application for the Sewer Line Upgrade/Replacement Project, finding it technically feasible, and recommended the Board as eligible to pursue the following funding:

$4,483,403
total estimated Phase I cost
$3,000,000
grant and principal forgiveness
$3,096,800
construction
Funding sourceAmount
WV DEP Clean Water State Revolving Fund (CWSRF) – principal forgiveness loan (does not have to be repaid)$2,000,000
WV DEP CWSRF loan – 0% interest, 0.25% administrative fee, 40 years$1,337,403
WV IJDC grant$1,000,000
Town of Chesapeake American Rescue Plan Act (ARPA) funds – committed$146,000
Total estimated project cost$4,483,403

Major costs: construction $3,096,800 plus $309,700 construction contingency; engineering, inspection and camera inspection of sewer lines by Burgess & Niple; legal, administrative, easement and permit costs; and a project contingency. The CWSRF loan also repays $185,703 that IJDC advanced for the project’s earlier planning and design phase. The Town separately contributed $224,702.74 of its ARPA funds during that earlier phase.

Sources: IJDC funding decision letter, January 7, 2026; Regional Intergovernmental Council revised Schedule B, December 15, 2025.

Proposed Sewer Rates – Rule 42 Summary

To pay for operating the sewer system and the project, the Sanitary Board has a Rule 42 rate summary, prepared by its certified public accountants, Bennett & Dobbins, for the Public Service Commission. These rates are proposed and are not in effect. Current rates remain as shown on the Sanitary Board WV State Code & Ordinance page.

  • 31% total increase in two steps:
    • Step 1 – 24% immediately (January 1, 2027), for cash flow: to bring rates up to the current cost of operating and maintaining the sewer system.
    • Step 2 – 7% after completion of the project (TBD 2+ years): to pay the project’s added costs, including the low-interest state loan payments, electricity for the new lift stations and project depreciation.

Proposed rates based on the current Tariff P.S.C. W. Va. No. 6, shown separately for each customer class. The increase is in two steps: 24% immediately (January 1, 2027) and 7% after completion of the project (TBD 2+ years), for 31% in total. Customers inside the Town limits also pay the 2% municipal utility tax surcharge, which is not included below.

Residential customers

Rate block (per 1,000 gallons)Current Tariff No. 6Step 1: +24% immediately (Jan. 1, 2027)Step 2: +7% after project completion (TBD 2+ years) (31% total)
First 2,000 gallons$23.26$28.84$30.47
Next 3,000 gallons$12.24$15.18$16.03
Next 10,000 gallons$8.56$10.61$11.21
All over 15,000 gallons$5.49$6.81$7.19
Minimum monthly charge$46.52$57.68$60.94

Example monthly residential bills:

ResidentialMinimum2,861 gal3,400 gal4,000 gal
Current$46.52$57.06$63.66$71.00
Step 1: +24% immediately (Jan. 1, 2027)$57.68$70.75$78.93$88.04
  Increase$11.16$13.69$15.27$17.04
Step 2: +7% after project completion (TBD 2+ years)$60.94$74.74$83.38$93.00
  Additional increase$3.26$3.99$4.45$4.96
Total increase (31%)$14.42$17.68$19.72$22.00

Commercial customers

Rate block (per 1,000 gallons)Current Tariff No. 6Step 1: +24% immediately (Jan. 1, 2027)Step 2: +7% after project completion (TBD 2+ years) (31% total)
First 2,000 gallons$25.68$31.84$33.64
Next 3,000 gallons$14.67$18.19$19.22
Next 10,000 gallons$10.40$12.90$13.62
All over 15,000 gallons$6.75$8.37$8.84
Minimum monthly charge$51.36$63.69$67.28

Example monthly commercial bills:

CommercialMinimum2,861 gal3,400 gal4,000 gal
Current$51.36$63.99$71.90$80.70
Step 1: +24% immediately (Jan. 1, 2027)$63.69$79.35$89.16$100.07
  Increase$12.33$15.36$17.26$19.37
Step 2: +7% after project completion (TBD 2+ years)$67.28$83.83$94.19$105.72
  Additional increase$3.59$4.48$5.03$5.65
Total increase (31%)$15.92$19.84$22.29$25.02

Phase 2 and future rates. Phase 2 will require a sewer system consolidation assessment before it moves forward. The 7% Step 2 increase follows completion of the project (TBD 2+ years).

Project cost in the rate summary: $4,709,106. This total includes the earlier planning and design phase: Town ARPA funds $371,703; IJDC planning grant $185,703; IJDC grant $814,297; CWSRF principal forgiveness $2,000,000; and CWSRF loan $1,337,403 (40 years).

Source: Rule 42 Summary Sheet prepared by Bennett & Dobbins, CPAs, for the Town of Chesapeake Sanitary Board.

Progress
  • Design is approaching 60% completion, with a review meeting with Chesapeake Operations on proposed sewer line and pump station layouts.
  • Easement drawings will follow the 60% review, and the Town will begin acquiring easements.
  • The WV DEP State Revolving Fund program returned minor comments on the Facilities Plan, and revisions were resubmitted. The overall schedule remains on track.
  • Any change affecting a requirement or the design comes to the Sanitary Board for review and approval.

More about the sewer system: Sanitary Services – Sewer System.