November 20, 2026

Proposed Sewer Rate Increase

The City of Chesapeake Sanitary Board has proposed a sewer rate increase to cover the current cost of operating the sewer system and to help pay for the Sewer Rehabilitation – Wastewater System Improvements project. These rates are proposed and are not in effect. Current sewer rates remain in place.

What is proposed

The proposed rates come from the Rule 42 rate analysis prepared by the Sanitary Board’s certified public accountants, Bennett & Dobbins.

  • 31% total increase in two steps:
    • Step 1 – 24% immediately (January 1, 2027), for cash flow: to bring rates up to the current cost of operating and maintaining the sewer system.
    • Step 2 – 7% after completion of the project (TBD 2+ years): to pay the project’s added costs, including the low-interest state loan payments, electricity for the new lift stations and project depreciation.

Proposed rates based on the current Tariff P.S.C. W. Va. No. 6, shown separately for each customer class. The increase is in two steps: 24% immediately (January 1, 2027) and 7% after completion of the project (TBD 2+ years), for 31% in total. Customers inside the Town limits also pay the 2% municipal utility tax surcharge, which is not included below.

Residential customers

Rate block (per 1,000 gallons)Current Tariff No. 6Step 1: +24% immediately (Jan. 1, 2027)Step 2: +7% after project completion (TBD 2+ years) (31% total)
First 2,000 gallons$23.26$28.84$30.47
Next 3,000 gallons$12.24$15.18$16.03
Next 10,000 gallons$8.56$10.61$11.21
All over 15,000 gallons$5.49$6.81$7.19
Minimum monthly charge$46.52$57.68$60.94

Example monthly residential bills:

ResidentialMinimum2,861 gal3,400 gal4,000 gal
Current$46.52$57.06$63.66$71.00
Step 1: +24% immediately (Jan. 1, 2027)$57.68$70.75$78.93$88.04
  Increase$11.16$13.69$15.27$17.04
Step 2: +7% after project completion (TBD 2+ years)$60.94$74.74$83.38$93.00
  Additional increase$3.26$3.99$4.45$4.96
Total increase (31%)$14.42$17.68$19.72$22.00

Commercial customers

Rate block (per 1,000 gallons)Current Tariff No. 6Step 1: +24% immediately (Jan. 1, 2027)Step 2: +7% after project completion (TBD 2+ years) (31% total)
First 2,000 gallons$25.68$31.84$33.64
Next 3,000 gallons$14.67$18.19$19.22
Next 10,000 gallons$10.40$12.90$13.62
All over 15,000 gallons$6.75$8.37$8.84
Minimum monthly charge$51.36$63.69$67.28

Example monthly commercial bills:

CommercialMinimum2,861 gal3,400 gal4,000 gal
Current$51.36$63.99$71.90$80.70
Step 1: +24% immediately (Jan. 1, 2027)$63.69$79.35$89.16$100.07
  Increase$12.33$15.36$17.26$19.37
Step 2: +7% after project completion (TBD 2+ years)$67.28$83.83$94.19$105.72
  Additional increase$3.59$4.48$5.03$5.65
Total increase (31%)$15.92$19.84$22.29$25.02
Public notice flyer: Proposed Sewer Rate Increase public meetings, Monday December 7 and Monday December 14, 2026 at 6:00 PM, with public hearing December 14, at the Dr. Lisa E. Curry Memorial Building Annex

View or print the flyer

How Chesapeake compares

Residential sewer bill for 4,000 gallons a month, nearby utilities.

Utility4,000 gal
South Charleston Sanitary Board$43.34
Town of Poca$47.29
Charleston Sanitary Board$57.04
St. Albans Municipal Utility Comm.$58.60
Town of Marmet$59.32
Dunbar Sanitary Board$61.74
Town of Pratt$66.02
Greater St. Albans PSD$67.54
West Dunbar PSD$68.36
Chesapeake – current$71.00
City of Montgomery$73.24
West Virginia-American Water (Kanawha)$78.09
Town of Belle$84.86
Town of Handley$85.20
Kanawha PSD (formerly Chelyan)$86.96
City of Smithers$87.64
Chesapeake – Jan. 1, 2027 (+24%)$88.04
Town of East Bank$88.80
Chesapeake – after project (+31%)$93.00
Town of Glasgow$96.92
Town of Cedar Grove$103.40

Source: WV Public Service Commission, Sewer Utility Cost Ranking – 4,000 Gallons (November 13, 2026), current tariffs. Proposed Chesapeake rates are shown against other utilities’ current rates. Statewide, Chesapeake’s current bill ranks 212th of 306 sewer utilities.

Why

Chesapeake’s sewer system was built in 1964. This is its first rehabilitation project.

  • Mandated sewer changes: a 2016 WV Department of Environmental Protection mandate requires removal of the sewer outfalls to the river.
  • Aging system: stormwater and groundwater leaking into aging sewer lines have overloaded the lift stations and caused sewer overflows.
  • Phase 1 work: replaces two lift stations, builds a force main to the treatment plant, and replaces sewer lines on Venable Ave., Kanawha Ave., 115th St. and Nancy Ave.
  • Keeping costs down: Phase 1 is funded with $3,000,000 in grants and principal forgiveness that does not have to be repaid, $146,000 in Town ARPA funds, and a low-interest 40-year state loan.

Phase 2 and future rates. Phase 2 will require a sewer system consolidation assessment before it moves forward. The 7% Step 2 increase follows completion of the project (TBD 2+ years).

What happens next

The proposed rates must be approved by Town Council before they take effect. Public notice will be given before Council acts, and residents will have the opportunity to comment.

Read more about the Sewer Rehabilitation project, funding and proposed rates · Current sewer rates

Questions: Town Hall, 304-949-1496 or townhall@chesapeakewv.gov.